The fit out, designed by architects Davenport Campbell, was completed in parallel to the completion of the base building construction, and required Peloton to work closely with the head contractor in respect to materials handling, programming and access issues.

The fit out extended over three floors, including out-door function areas and shade structures.

The main difficulties faced during this project were with the materials handling. This was due to the base building head contractor still controlling the site with minimal lift access and the location of the building being on one of Sydney CBD’s busiest intersections.

Peloton delivered the project on time and within expectation despite only having 5 months from commencing design development to practical completion.

The works were completed over 12 weeks.